America's largest power grid struggles to meet demand amid a tech industry power grab—but that's not the only issue.
Electricity bills are projected to surge by more than 20% this summer in some parts of PJM Interconnection's territory, which covers 13 states.
The region, which has the country's most concentrated cluster of data centres, is experiencing a surge in energy consumption that outpaces new plant construction.
America's largest power grid struggles to meet demand amid a tech industry power grab—but that's not the only issue.
HARRISBURG, Pennsylvania (Reuters) -America's largest power grid is under strain as data centers and AI chatbots consume ...
Some parts of PJM Interconnection's power grid are expected to use up so much electricity that people's bills for the summer ...
During a recent heat wave, PJM Interconnection, the Midwest's electric grid operator, found itself operating at 163,000 megawatts, flirting with the grid's all-time peak usage record of 165,000 ...
The high temperatures and humidity that the Tri-State Area has experienced during the past several weeks has led to many households cranking up the air conditioning and using plenty of electricity.
By the numbers It takes one megawatt to power about 800 homes, PJM said. It has 179,200 megawatts of generation capacity and can call on some users to provide another 7,900 megawatts if needed by ...
Pennsylvania Governor Josh Shapiro filed a complaint with a federal energy regulator against PJM Interconnection on Monday, arguing that the largest U.S. power grid operator must change its market ...
Artificial Intelligence consumes as much as 20 percent of global data-center power demand, based on research published in the ...